Electrical grids of JSC "Grid Company" are the part of the unified system of Povolzhie and RAO UES Russia.
Electricity is transferred along the aerial and cable lines of the 9 branches of JSC "Grid Company". About 10 th. km of electricity transmission lines of 35-500 kV voltage cover the territory of Republic. The length of the lines of 6-10 kV is 23.7 th. km, and the lines 0.4 kV - 27.1 th. km.
Grid entities of JSC "Grid Company" operate 374 substations voltage of 35 kV and higher, as well as 18,792 transformers of 6-10 kV operating in 16,412 transformer substations and distribution stations.
Branches of JSC "Grid Company" are Almetievsk, Bugulma, Buinsk, Yelabuga, Kazan, Nizhnekamsk , Naberezhnye Chelny , Privolzhskie, Chistopol electrical grids.
| Grid branches |
HL 0.4 - 500kV |
KL 0.4 -110 kV |
Substations |
| Total length (along the track) km |
Voltage kV |
Total length |
Number of SS 35-500 kV, units |
Total installed capacity MW |
| Almetievsk El. Grids |
7030 |
0,4 - 220kV |
533,4 |
52 |
3496 |
| Bugulma El. Grids |
6677 |
0,4 - 500kV |
338,6 |
51 |
3076 |
| Buinsk El. Grids |
8936 |
0,4 - 220kV |
24,5 |
43 |
1241 |
| Yelabuga El. Grids |
8685 |
0,4 - 220kV |
446,7 |
47 |
1639 |
| Kazan El. Grids |
2445 |
0,4 - 500kV |
2796,7 |
27 |
5195 |
| Nizhnekamsk El. Grids |
7174 |
0,4 - 500kV |
1581,0 |
44 |
2323 |
| Naberezhnye Chelny El. Grids |
322 |
0,4 - 110kV |
2010,1 |
12 |
1242 |
| Privolzhskie El. Grids |
10137 |
0,4 - 220kV |
270,1 |
54 |
1830 |
| Chistopol El. Grids |
9366 |
0,4 - 220kV |
108,9 |
44 |
1360 |
With absolute reliable electricity supply to Republican consumers, the basic task of JSC "Grid Company" today is to reduce the costs of electricity transportation.
|