Basing on results for 2007 the JSC "Tatenergo " is among the fifty most environmentally responsible companies of Russia. The amount of prevented environmental damage by the Holding entities in 2007 constituted over 30 million rubles .
Main page Production Investments and Innovations Capital Construction and Technical Refurbishment
Investments and Innovations
Research and Technical Policy
Program for Cost Management
Information Technologies
Capital Construction and Technical Refurbishment
Investment Projects
Environmental Policy
Capital Construction and Technical Refurbishment

Power Engineering

JSC "Generation Company"

In JSC "Generation Company" implementation of plans of capital construction in 2007 allowed to:

  • do reconstruction of coal-fired boiler, reconstruction of outside switchgear ORU -110 kV and install hydro clutch at PEN of Kazan CHP-2;
  • do reconstruction of cogeneration schemes at Naberezhnye Chelny CHP and Kazan CHP-1;
  • do reconstruction of the cool tower at Kazan CHP-2 and Naberezhnye Chelny CHP;
  • do reconstruction of slime pit at Kazan CHP-3;
  • install system of ball cleaning of turbine condensers on 4 units of Zainsk Condensation Plant;
  • start designing of SGT at Kazan CHP-1 and CHP-3, Zainsk Condensation Plant and Yelabuga CHP.
Kazan CHP-3. Slime pit Kazan CHP-2. Cool towers
Kazan CHP-3.
Slime pit
Kazan CHP-2.
Cool towers
Zainsk Condensation Plant. System of ball cleaning Zainsk Condensation Plant. System of ball cleaning
Zainsk Condensation Plant.
System of ball cleaning
Zainsk Condensation Plant.
System of ball cleaning


JSC "Network Company"

In JSC "Network Company" in 2007:

  • done reconstruction of SS 110-220 kV "Vostochnaya" and "Zapadnaya" of Kazan grids, "Abdrahmanovo" of Almetievsk grids, "Nizhnekamsk" of Nizhnekamsk grids and "Nurlat" of Chistopol grids;
  • done reconstruction of HL 110 kV "Uzlovaya – Severozapadnaya – Àktash – Zainsk" and "Kazan CHP-3 – Severnaya".
Kazan Electrical Networks. SS "Vostochnaya" Kazan Electrical Networks. SS "Vostochnaya"
Kazan Electrical Networks.
SS "Vostochnaya"
Kazan Electrical Networks.
SS "Vostochnaya"

JSC "Dispatch Center"

In JSC "Dispatch Center" in 2007:

  • done reconstruction of systems of anti-accident automatics of SS "Kinderi" of Kazan grids and SS "Bugulma-500" of Bugulma grids;
  • done reconstruction of Hl 220 kV "Nizhnekamsk – Bukash " and "Kinderi – Zeleny Dol".
Kazan Electrical Networks.  SS "Kinderi" Kazan Electrical Networks.  SS "Kinderi"
Kazan Electrical Networks.
SS "Kinderi"
Kazan Electrical Networks.
SS "Kinderi"
Bugulma Electrical Networks Bugulma Electrical Networksåòè
Bugulma Electrical Networks.
SS "Bugulma-500"
Bugulma Electrical Networks.
SS "Bugulma-500"


JSC "Kazan Thermal Network Company"

In JSC "Kazan Thermal Network Company" in 2007:

  • done reconstruction of in-quarter networks of TS and GVS in Central, Southern, Eastern and Northern operational districts of Kazan;
  • done reconstruction of parts of heat pipelines #13, 14 from Kazan CHP-2;
  • were installed the meters of heat at the trunk heat pipelines.
JSC "Kazan Thermal Network Company" JSC "Kazan Thermal Network Company"
JSC "Kazan Thermal Network Company".
Heat Pipeline of Kazan CHP-2
JSC "Kazan Thermal Network Company".
Reconstruction of Heat Pipeline
Reconstruction  of central thermal stations Reconstruction  of central thermal stations
Reconstruction of central thermal stationsReconstruction of central thermal stations


JSC "Naberezhnye Chelny Thermal Network Company"

In JSC "Naberezhnye Chelny Thermal Network Company" in 2007:

  • done reconstruction of heat pipelines #110 and #210 in Naberezhnye Chelny;
  • done reconstruction of electrical part of PNS – 1, 2, 3 in Nizhnekamsk.
Nizhnekamsk PNS Nizhnekamsk PNS
Nizhnekamsk PNS Nizhnekamsk PNS

Besides in 2007 the overhaul was made at:

  • in JSC "Generation Company";
  • in JSC "Network Company";
  • in JSC "Kazan Thermal Network Company";
  • in JSC "Tatenergo".